Kitchen, 1926 bungalow · Plaza Midwood

The Build Ledger

One kitchen, 17 weeks, every number — including the $6,800 we went over and the 3 weeks we ran late.

Every builder in Charlotte has beautiful photographs. None of them will show you what the job actually cost, because the overruns look bad in isolation. They are not bad in isolation — they are what a hundred-year-old house does when you open it, and the only question is whether you find out before or after you sign.

So here is one, in full. Seventeen rows. Open any of them for what changed and who decided.

A note on what this is: a worked example, built to show the format and the level of detail. The format is exactly what you get during a project with us — the same columns, updated weekly, for your own house.

Week by week

168 sq ft, walls unchanged, one window enlarged. Rows with a marker opened up — tap any of them for what changed and who decided.

How it closed out

Estimated
$94,500
Planned
14 weeks
Final
$101,300
Actual
17 weeks
Over
+$6,800
Late
+3 weeks

That is 7.2% over on money and 21 days over on time, on a 168 sq ft, walls unchanged, one window enlarged kitchen in a Plaza Midwood bungalow. Neither number is zero, and any builder who shows you one that is has either not built it yet or is not showing you everything.

What happens with yours

Yours will have its own version of this.

Different surprises, different numbers. We cannot tell you what is under your sink window any more than we could tell that client — but we can tell you what the room costs, how long it takes, and where the risk sits, before you commit to building anything.

The design agreement is $3,500 for a kitchen or bathroom and $6,500 for whole-home or an addition, and it produces the first three columns of this ledger — the weeks, the work and the estimate — before you commit to anything. Credited in full against construction if you build.

Licensed
DEMO-GC-78412
North Carolina Licensing Board for General Contractors
Insured and bonded
General liability, $2,000,000 aggregate
Certificates come to you from the carrier, not from us
Building since
2014
12 years in Charlotte

Take it with you

Not ready to spend anything? Take the ledger instead.

Useful for reading against somebody else’s bid. If a builder’s schedule has no float in it and their estimate has no contingency, you now know what that means.

All seventeen weeks, with the change notes. One email, no follow-up.

An interior corner during demolition: a stud wall opened up beside a pale green plastered wall, an electrical box hacked out of the plaster, a taped no-smoking sign, and a date pencilled on the wall.
Week six on somebody's job. The pencil date on the plaster is how a site actually records itself — and it's the same information we put in your ledger, just legible.
Request the design agreementCall